KCMetroLogo

Daily Traffic Information

for the weekend of

Friday-Monday, July 11-14, 2014

 

(NEW - REVISED)

  


  

SHORT TERM

  

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY

> > #Jocogateway

I-35 & I-435 Interchange

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Eastbound I-435 ONE LEFT LANE from 87th Street to Quivira Road will be CLOSED for temporary pavement marking and sign work from 8:00 p.m. to 10:00 p.m. on Wednesday-Friday, July 9-11; then eastbound I-435 TWO LEFT LANES from I-35 to Quivira Road will be CLOSED overnight beginning at 10:00 p.m. and will reopen to all traffic at 5:00 a.m. the next morning, on Wednesday-Friday, July 9-11. Project work is scheduled to be completed on Saturday, July 12. (New 7-7-14)

EXPECT DELAYS! WEEKEND DAY LANE CLOSURE: Eastbound I-435 left lane from 87th Street to Quivira Road will be CLOSED for temporary striping and sign work on Saturday, July 12 between 5:00 a.m and 10:00 a.m. Project work is scheduled to be completed on Saturday, July 12.  (New 7-11-14)

K-10 & Ridgeview Road Interchange

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Eastbound and westbound K-10 RIGHT LANES at Ridgeview Road will be CLOSED for median island (on bridge) demolition work on Monday-Wednesday, July 14-16 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Wednesday, July 16.  (New 7-11-14)

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURES: Eastbound and westbound K-10 LEFT LANES at Ridgeview Road will be CLOSED for median island (on bridge) demolition work on Thursday-Friday, July 17-18 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Friday, July 18. (New 7-11-14)

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound and southbound Ridgeview Road left turn lanes on K-10 bridge will be CLOSED for median island (on bridge) demolition work on Monday-Friday, July 14-18 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Friday, July 18. (New 7-11-14)

 


 

Northbound I-35 & Johnson Drive Interchange

EXPECT DELAYS! WEEKEND 24/7 RAMP CLOSURES: Northbound I-35 at Johnson Drive entrance and exit ramps will be CLOSED, 24/7 round the clock, for concrete pavement patching and replacement work on the interchange ramps beginning at 7:00 p.m. on Friday, July 11 and reopening to all traffic at 5:00 a.m. on Monday, July 14, weather permitting. The same work will then be repeated weather permitting for the following weekend of Friday-Monday, July 18-21. A marked detour will be provided. Northbound I-35 traffic will detour via the Antioch Road exit then head back south on I-35 to Johnson Drive. Johnson Drive traffic will detour either to the south and use Shawnee Mission Parkway to turn around and head back north or will detour to the north on Antioch Road to I-35. Project work is scheduled to be completed on Monday, July 14. (New 7-8-14)

EXPECT DELAYS! UPCOMING WEEKEND 24/7 RAMP CLOSURES: Northbound I-35 at Johnson Drive entrance and exit ramps will be CLOSED, 24/7 round the clock, for concrete pavement patching and replacement work on the interchange ramps beginning at 7:00 p.m. on Friday, July 18 and reopening to all traffic at 5:00 a.m. on Monday, July 21. A marked detour will be provided. Northbound I-35 traffic will detour via the Antioch Road exit then head back south on I-35 to Johnson Drive. Johnson Drive traffic will detour either to the south and use Shawnee Mission Parkway to turn around and head back north or will detour to the north on Antioch Road to I-35. Project work is scheduled to be completed on Monday, July 21. (New 7-8-14)

I-35 & 75th Street Interchange Ramp Closures
Overall project work is scheduled to be completed in late August 2014

EXPECT DELAYS! 24/7 RAMP CLOSURES: Northbound I-35 to 75th Street exit ramp and 75th Street to southbound I-35 entrance ramp will be CLOSED, 24/7 round the clock, for pavement repair work for a City of Overland Park construction project beginning at 11:00 a.m. on Thursday, July 10 through late August 2014, weather permitting. The 75th Street to northbound I-35 entrance ramp will be restricted to right turns only during this same timeframe. Marked detours will be provided. Northbound I-35 traffic will detour via 67th Street exit and take eastbound 67th Street to Antioch Road, then southbound Antioch Road to eastbound 75th Street back to northbound I-35. 75th Street to southbound I-35 traffic will proceed eastbound on 75th Street across the bridge over I-35 to Antioch Road, then northbound on Antioch Road to westbound 67th Street back to southbound I-35. Project work is scheduled to be completed in late August 2014. (New 7-9-14)

I-435 & Roe Avenue Diverging Diamond Interchange Project
Overall project work is scheduled to be completed by late November 2014

EXPECT DELAYS! WEEKEND DAY LANE CLOSURE: Eastbound I-435 left lane at Roe Avenue will be CLOSED for bridge work on Saturday, July 12 between 7:00 a.m. and 3:00 p.m. Project work is scheduled to be compelted on Saturday, July 12. (New 7-10-14)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound I-435 left lane and westbound I-435 right lane at Roe Avenue will be CLOSED for bridge work on Monday, July 14 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Monday, July 14. (New 7-10-14)

K-7/U.S. 169/151st Street & I-35 Interchange

EXPECT DELAYS! 24/7 WEEKEND CLOSURES:  Lane and ramp closures at the K-7/U.S. 169/151st Street and I-35 interchange will occur for pavement reconstruction work on the north side of the interchange for the weekend beginning at 9:00 p.m. on Friday, July 11 to all traffic at 5:00 a.m. on Monday, July 14. Project work is scheduled to be completed on Monday, July 14. (Rev. 6-30-14)

Weekend of July 11-14:

151st Street/K-7/U.S. 169 Interchange on the north side of 151st Street and the southbound I-35 exit ramp to K-7/151st Street will be CLOSED, although southbound K-7 traffic will still be allowed through the intersection. Detour: Southbound I-35 traffic will exit at Old U.S. 56 and go west to K-7 following the existing detour. Northbound K-7 traffic will detour west on 151st Street and then north on Lone Elm Road.

K-10

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Westbound Left lane closed from Ridgeview Road to Little Mill Creek for guardrail repair work on Monday, July 14 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Monday, July 14. (New 7-11-14)

U.S. 56 over I-35 Bridge Repair Project
Overall project work is scheduled to be completed in late October 2014

EXPECT DELAYS! 24/7 LANE CLOSURES: Eastbound and westbound U.S. 56 over the I-35 bridges will be reduced to one lane each direction for bridge repair and overly work, 24/7 round the clock, beginning at 9:00 a.m. on Monday, July 14 throughout the project duration. All interchange ramps will remain open. Project work is scheduled to be completed in late October 2014. (New 7-11-14) 

 

LEAVENWORTH COUNTY

 

No project closures at this time.

 

WYANDOTTE COUNTY 

 

I-70 & K-7 Interchange Project
Overall project work scheduled to be completed in late Fall 2014

I-70

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Westbound I-70 left lane at K-7 will be CLOSED for bridge work on Saturday, July 12 between 9:00 a.m. and 3:30 p.m. Project work is scheduled to be completed on Saturday, July 12.(New 7-11-14)

I-70 from 110th Street to I-435 Resurfacing Project
Overall project work scheduled to be completed in mid-July 2014

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Eastbound and westbound I-70 from 118th Street to I-435 will be reduced to ONE OPEN LANE each direction and have various short-term closures for saw and seal work on pavement joints on Monday-Friday, July 7-12 between 7:00 p.m. and 6:00 a.m. each day. Project work is scheduled to be completed on Saturday, July 13. (New 7-3-14)

I-635 at Gibbs Road Bridge Replacement Project

EXPECT DELAYS! 24/7 LANE CLOSURES: Northbound I-635 at Gibbs Road bridge location will be reduced to TWO OPEN LANES for setting of bridge girders, 24/7 round the clock, on Tuesday-Friday, July 15-25, except for times noted below. Project work is scheduled to be completed on Friday, July 25. (New 7-11-14)

EXPECT DELAYS! OVERNIGHT LANE CLOSURES: Northbound I-635 at Gibbs Road bridge location will be reduced to ONE OPEN LANE for setting of bridge girders, 24/7 round the clock, beginning at 6:00 p.m. on Monday, July 14 and reopening at 6:00 a.m. on Tuesday, July 15 and repeating through 6:00 a.m. on Thursday, July 17. Project work is scheduled to be completed on Thursday, July 17. (New 7-11-14)

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Northbound I-635 at Gibbs Road bridge location will be reduced to ONE OPEN LANE for setting of bridge girders on Monday-Friday, July 14-25 between 9:00 a.m. and 3:30 p.m. daily. Project work is scheduled to be completed on Friday, July 25. (New 7-11-14)

 


  

LONG TERM

  

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY 

 

I-35 Spoon Creek & Bull Creek Bridge Repair Project
Overall project work is scheduled to be completed in September 2014

EXPECT DELAYS! 24/7 LANE CLOSURES: Northbound and southbound I-35 over Spoon Creek and Bull Creek between Sunflower Road and Homestead Lane exits will be reduced to one lane each direction, 24/7 round the clock, for bridge repair work beginning at 7:00 a.m. on Monday, June 2, through early September 2014. Project work is scheduled to be completed in early September 2014. (New 5-30-14)

I-435 at 87th Street Bridge Repair Project
Overall project work is scheduled to be completed by late August 2014

EXPECT DELAYS! 24/7 LANE CLOSURES: Northbound I-435 at 87th Street will be reduced to two open lanes beginning at 9:00 a.m. on Wednesday, May 14 and then at 9:00 a.m. on Thursday, May 15, southbound I-435 at 87th Street will be reduced to two open lanes and these lane closures will remain in place, 24/7 round the clock, throughout the project duration for bridge repair work. Project work is scheduled to be completed in late August 2014. (Rev. 5-12-14)

I-435 & Roe Avenue Diverging Diamond Interchange Project
Overall project work is scheduled to be completed by late November 2014

EXPECT DELAYS! 24/7 ROADWAY CLOSURE: Roe Avenue over I-435 will be CLOSED to all traffic through beginning at 9:00 a.m. on Friday, May 30, as crews complete construction work on the new Roe Avenue bridges. Marked detours will be provided. Project work is scheduled to be completed in late October 2014.(New 5-28-14)

24/7 RAMP LANE CLOSURE: Westbound I-435 to Roe Avenue entrance ramp left turn lane will be CLOSED, 24/7 round the clock beginning on Wednesday, May 28 at 9:00 a.m. for bridge replacement work. Project work is scheduled to be completed in late October 2014. (Rev. 5-30-14)

24/7 RAMP LANE CLOSURES: All left turn movements from eastbound I-435 ramps to Roe Avenue will be CLOSED, 24/7 round the clock beginning on Thursday, May 29 at 9:00 a.m. for bridge replacement work. Project work is scheduled to be completed in late October 2014. (Rev. 5-30-14)

K-7/U.S. 169 at I-35 Pavement Replacement Project
Overall project work is scheduled to be completed by late September 2014

EXPECT DELAYS! FULL ROADWAY CLOSURE: Northbound and southbound K-7/U.S. 169 will be CLOSED to through traffic between the northbound and southbound I-35 exit ramps for pavement replacement work beginning on Monday, April 28, sometime after morning rush hour, through mid-July 2014. A marked detour will be provided. Traffic will detour via the interchange ramps. Access will be maintained to local businesses throughout the project duration. This portion of the project work is scheduled to be completed in mid-July 2014. (New 4-23-14)

K-10 Over Evening Star Road and Edgerton Road Bridge Repair Project
Overall project work scheduled to be completed in early September 2014

EXPECT DELAYS! 24/7 LANE CLOSURE: Eastbound K-10 from west of the Evening Star Road bridge to east of the Edgerton Road bridge will be reduced to one lane, 24/7 round the clock, for bridge repair work beginning at 7:00 a.m. on Monday, June 23. Project work is scheduled to be completed in early September 2014. (New 6-16-14) 

U.S. 56 over I-35 Bridge Repair Project
Overall project work is scheduled to be completed in late October 2014

EXPECT DELAYS! 24/7 LANE CLOSURES: Eastbound and westbound U.S. 56 over the I-35 bridges will be reduced to one lane each direction for bridge repair and overly work, 24/7 round the clock, beginning at 9:00 a.m. on Monday, July 14 throughout the project duration. All interchange ramps will remain open. Project work is scheduled to be completed in late October 2014. (New 7-11-14) 

 

 

LEAVENWORTH COUNTY

 

U.S. 73 / K-7 Pavement Replacement Project
Overall project work is scheduled to be completed in late December 2014

24/7 LANE CLOSURES: Northbound and southbound U.S. 73/K-7 from 20th Street to the north junction of Leavenworth County Road 14/Santa Fe Trail will be CLOSED to all traffic beginning at 8:00 a.m. on Monday, July 7 for pavement replacement work. A marked detour will be provided via Leavenworth County Road 14. Project work is scheduled to be completed in late December 2014. (New 7-3-14)

 

WYANDOTTE COUNTY

 

I-70 & K-7 Interchange Project
Overall project work scheduled to be completed in late Fall 2014

K-7

24/7 LANE CLOSURES: Northbound and southbound K-7 from south of Kansas Avenue to north of Riverview Avenue will be shifted and placed one lane each direction, side by side, onto the existing southbound lanes while the northbound lanes are reconstructed, beginning sometime after morning rush hour on Thursday, June 11 through late August 2014, weather permitting. Also, the I-70 to southbound K-7 double left turn lane movement will remain reduced to ONE OPEN left turn lane throughout the project duration. See map above for traffic shift configuration. Project work is scheduled to be completed in late August 2014. (New 6-11-14)

24/7 TRAFFIC SHIFT: Eastbound I-70/Kansas Turnpike from 134th Street to just west of K-7 will be shifted to the north and restricted to two 12-foot wide lanes reducing both inside and outside shoulders to 4-foot each. This traffic shift is needed for adjacent ramp construction work for Phase One of the K-7 & I-70 Interchange Project in Wyandotte County. Project work is scheduled to be completed in early October 2014. (New 4-28-14)

118th Street Over I-70 Bridge Replacement Project
Overall project work is scheduled to be completed in mid-November 2014

24/7 BRIDGE CLOSURE: 118th Street from Riverview Avenue to Speedway Boulevard will be CLOSED to all traffic for bridge replacement work beginning on Monday, March 17, 24/7 round the clock, throughout the project duration. A marked detour will be provided via 110th Street. Access to Sunflower Hills Golf Course will remain open during the project duration. For golf course access, drivers will continue on Riverview Avenue to Tom Lally Drive. Project work is scheduled to be completed in mid-November 2014. (New 3-21-14)

Gibbs Road over I-635 Bridge Replacement Project
Overall project work is scheduled to be completed in early September 2014

WEEKDAY OVERNIGHT LANE CLOSURES: Southbound I-635 right exit lane off of Metropolitan Avenue that serves as entrance lane to Shawnee Drive will be CLOSED for bridge construction work on Monday-Friday, June 23-August 1 between 9:00 a.m. and 3:00 p.m. each day. Project work is scheduled to be completed on Friday, August 1. (New 6-24-14)

24/7 LANE CLOSURE: Southbound I-635 left lane at Gibbs Road will be CLOSED for eight consecutive weeks, 24/7 round the clock, beginning after morning rush hour on Tuesday, May 20 through late July, for bridge pier construction work on the new Gibbs Road Bridge over I-635. Project work is scheduled to be completed in late July. (New 5-20-14)

24/7 ROADWAY CLOSURE: Eastbound and westbound Gibbs Road from 42nd Street to 47th Street will be CLOSED to all through traffic, 24/7 round the clock, beginning on Monday, May 5, after morning rush hour, throughout the project duration. A marked detour will be provided. Traffic will detour via 42nd and 47th Streets to Shawnee Drive. Overall project work is scheduled to be completed in early September 2014. (New 4-28-14)

U.S. 73 / K-7 at Piper Creek Bridge Replacement Project
Overall project work is scheduled to be completed in late September 2014

24/7 LANE CLOSURES: Northbound and southbound U.S. 73/K-7 traffic will be shifted and placed side by side, one lane each direction, in the existing northbound U.S. 73/K-7 lanes from Parallel Parkway to Donahoo Road for bridge replacement work beginning around 10:00 a.m., Monday, June 9 through late September 2014. Project work is scheduled to be completed in late September 2014. (Rev. 6-5-14)