KCMetroLogo

Daily Traffic Information

for the weekend of

 

Friday-Monday, April 24-27, 2015

 

(NEW - REVISED)

 


 

SHORT TERM

 

Short term project closures listed below typically take place during daylight hours. Project completion dates typically range from 1 to 30 days. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY

  >  >  #Jocogateway

 

Northbound I-35 Dedicated Through Lane

24/7 DEDICATED THROUGH LANE ADDITION: Northbound I-35 FAR LEFT LANE from I-435 to 95th Street will be shifted to the existing southbound I-35 far left lane (and placed between concrete barriers) to create a “dedicated through lane” beginning early morning on Sunday, April 26, weather permitting, so crews can complete widening work on northbound I-35 and on the Pflumm Road bridge. This lane is similar to the westbound I-435 left through lane that was created for ongoing construction work. This northbound I-35 dedicated through lane is scheduled to be removed from use in mid-July 2015. (NEW 4-23-15)

I-35 & I-435 Interchange Bridge Project

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURE: Westbound I-435 RIGHT LANE from U.S. 69 to Quivira Road will be CLOSED for pavement marking work beginning at 8:00 p.m. on Saturday, April 25 and reopening to all traffic at 5:00 a.m. on Sunday, April 26. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURE: Northbound I-35 ONE LEFT LANE from I-435 to 95th Street will be CLOSED for pavement marking work beginning at 8:00 p.m. on Saturday, April 25 and TWO LEFT LANES will be CLOSED beginning at 10:00 p.m. the same night and reopening to all traffic 5:00 a.m on Sunday, April 26. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-24-15) 

Traffic Pattern Change: Westbound I-435 RIGHT LANE from Quivira Road to I-35 will shift to the right on Saturday, April 25. With this traffic shift, traffic from Quivira Road to westbound I-435 will have to exit at I-35 thru Friday, May 1. (NEW 4-24-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Westbound I-435 FAR LEFT LANE (between barrier) from U.S. 69 to I-35 will be CLOSED for paving work on Monday, April 27 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Monday, April 27. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND OVERNIGHT RAMP LANE CLOSURE: U.S. 69 to westbound I-435 RIGHT RAMP LANE will be CLOSED for pavement marking work beginning at 10:00 p.m. on Saturday, April 25 and reopening to all traffic at 5:00 a.m. on Sunday, April 26. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND OVERNIGHT RAMP CLOSURES: The ramps from westbound I-435 to northbound I-35 and eastbound I-435 to northbound I-35 will be CLOSED for temporary asphalt work beginning at 10:00 p.m. Saturday, April 25 and reopening to all traffic at 5:00 a.m. on Sunday, April 26. Westbound I-435 to northbound I-35 ramp traffic to detour via northbound U.S. 69 or southbound I-35 to turn around at 119th Street to access northbound I-35. Eastbound I-435 to northbound I-35 ramp traffic to detour via eastbound I-435 to northbound U.S. 69 to access northbound I-35. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-23-15)

EXPECT DELAYS!  WEEKEND OVERNIGHT RAMP CLOSURE: Quivira Road to westbound I-435 ramp will be CLOSED for traffic switch work beginning at 10:00 p.m. Saturday, April 25 and reopening to all traffic at 5:00 a.m. on Sunday, April 26. Southbound Quivira Road traffic will detour via College Boulevard east to northbound U.S., 69; Northbound Quivira Road traffic will detour via 103rd Street east to southbound U.S. 69. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-23-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT RAMP CLOSURE: Quivira Road to westbound I-435 ramp will be CLOSED for traffic switch work beginning at 10:00 p.m. Monday-Wednesday, April 27-29 and reopening to all traffic at 5:00 a.m. on Tuesday-Thursday, April 28-30. Southbound Quivira Road traffic will detour via College Boulevard east to northbound U.S., 69; Northbound Quivira Road traffic will detour via 103rd Street east to southbound U.S. 69. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-23-15)

K-10 at Renner Boulevard to Ridgeview Road Interchanges

EXPECT DELAYS! WEEKDAY LANE CLOSURE: Eastbound K-10 LEFT LANE from Ridgeview Road to Renner Bouleavard will be CLOSED for sign truss work on Monday, April 27 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Monday, April 27. (NEW 4-24-15)

K-10 at I-435 Interchange

EXPECT DELAYS! UPCOMING WEEKDAY LANE CLOSURE: Westbound K-10 RIGHT LANE at I-435 will be CLOSED for concrete pour work on Tuesday, April 28 between 9:00 a.m. and 3:00 p.m. The Lackman Road entrance ramp traffic will need to merge during this timeframe. Project work is scheduled to be completed on Tuesday, April 28. (NEW 4-24-15)

College Boulevard

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Westbound College Boulevard RIGHT LANE just past Renner Boulevard will be CLOSED for concrete work beginning at 8:00 p.m. on Friday, April 24 and reopening at 12:00 p.m. NOON on Saturday, April 25. Turns will still be permitted via through lane. Project work is scheduled to be completed on Saturday, April 25. (NEW 4-23-15)

EXPECT DELAYS! WEEKEND DAY LANE CLOSURE: Southbound Ridgeview Road RIGHT LANE at College Boulevard inetersection will be CLOSED for finishing work on Saturday, April 25 between 9:00 a.m. and 5:00 p.m. Turns will still be permitted via through lane. Project work is scheduled to be completed on Saturday, April 25. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY LANE CLOSURES: Eastbound and westbound College Boulevard LEFT LANES from Renner Boulevard to Ridgeview Boulevard will be CLOSED for finishing work on Saturday, April 25 between 9:00 a.m. and 5:00 p.m. Turns will still be permitted via through lane. Project work is scheduled to be completed on Saturday, April 25. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURES: Eastbound and westbound College Boulevard at Renner Boulevard and Ridgeview Boulevard intersections will have varying lane closures for sensor loop installation work on beginning at 8:00 p.m. on Saturday-Sunday, April 25-26 and reopening to all traffic at 5:00 a.m. on Sunday-Monday, April 26-27. Turns will still be permitted via through lane. Project work is scheduled to be completed on Monday, April 27. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY LANE CLOSURES: Northbound and southbound Renner Bouleavard at College Boulevard will have ONE LANE CLOSED each direction for finishing work on Saturday, April 25 between 9:00 a.m. and 5:00 p.m. Turns will still be permitted via through lane. Project work is scheduled to be completed on Saturday, April 25. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURES: Northbound and southbound Renner Boulevard and northbound and southbound Ridgeview Road at College Boulevard intersection will have varying lane closures for sensor loop installation work beginning at 8:00 p.m. on Friday-Sunday, April 24-26 and reopening to all traffic at 5:00 a.m. on Saturday-Monday, April 25-27. Turns will still be permitted via through lane. Project work is scheduled to be completed on Monday, April 27. (NEW 4-24-15)

EXPECT DELAYS! WEEKEND DAY OVERNIGHT LANE CLOSURES: Northbound and southbound Ridgeview Road LEFT LANE at College Boulevard will be CLOSED for crack seal repair beginning at 8:00 p.m. on Saturday, April 25 and reopening to all traffic at 5:00 a.m. on Sunday, April 26. Project work is scheduled to be completed on Sunday, April 26. (NEW 4-23-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Westbound College Boulevard RIGHT LANE will be CLOSED just past Renner Boulevard for concrete work beginning at 8:00 p.m. on Friday, April 24 and reopening at 12:00 p.m. NOON on Saturday, 25. Turns will still be permitted via through lane. Project work is scheduled to be completed on Saturday, April 25. (NEW 4-23-15)

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Eastbound and westbound College Boulevard LEFT LANES from Renner Boulevard to Ridgeview Boulevard will be CLOSED for finishing work on Monday, April 27 between 9:00 a.m. and 5:00 p.m. Turns will still be permitted via through lane. Project work is scheduled to be completed on Moinday, April 27. (NEW 4-24-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Northbound and southbound Renner Boulevard and northbound and southbound Ridgeview Road at College Boulevard intersection will have varying lane closures for sensor loop installation work beginning at 8:00 p.m. on Monday, April 27 and reopening to all traffic at 5:00 a.m. on Tuesday, April 28. Turns will still be permitted via through lane. Project work is scheduled to be completed on Tuesday, April 28. (NEW 4-24-15)

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE CLOSURES: Eastbound and westbound College Boulevard at Renner Boulevard and Ridgeview Boulevard intersections will have varying lane closures for sensor loop installation work beginning at 8:00 p.m. on Monday, April 27 and reopening to all traffic at 5:00 a.m. on Tuesday, April 28. Turns will still be permitted via through lane. Project work is scheduled to be completed on Tuesday, April 28. (NEW 4-24-15)

Marshall Drive & 95th Street Intersection

EXPECT DELAYS! UPCOMING WEEKDAY OVERNIGHT FULL ROADWAY CLOSURE: Northbound and southbound Marshall Driver at 95th Street will be FULLY CLOSED for utility pohtoling work beginning at 10:00 p.m. on Tuesday-Wednesday, April 28-29 and reopening to all traffic at 5:00 a.m. on Wednesday-Thursday, April 29-30. Traffic will detour via 95th Street and Pflumm Road. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-24-15)

EXPECT DELAYS! UPCOMING WEEKDAY OVERNIGHT LANE CLOSURE: Eastbound 95th Street LEFT LANE at Marshall Drive will be CLOSED for utility pohtoling work beginning at 10:00 p.m. on Tuesday-Wednesday, April 28-29 and reopening to all traffic at 5:00 a.m. on Wednesday-Thursday, April 29-30. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-24-15)

Pflumm Road Under I-435

EXPECT DELAYS! UPCOMING WEEKDAY OVERNIGHT FULL ROADWAY CLOSURE: Northbound and southbound Pflumm Road under I-435 bridges will be FULLY CLOSED for I-435 bridge demolition work beginning at 10:00 p.m. on Wednesday, April 28 and reopening to all traffic at 5:00 a.m. on Thursday, April 30. Traffic will detour via College Boulevard, Quivira Road and 103rd Street. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-24-15)


U.S. 69 & 135th Street Interchange

EXPECT DELAYS! UPCOMING WEEKDAY RAMP LANE CLOSURE: Eastbound 135th Street to northbound U.S. 69 ramp will be CLOSED for core drilling work on Thursday, April 30 between 9:00 a.m. and 3:00 p.m. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-23-15) 

 

 

LEAVENWORTH COUNTY

 

 

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge

EXPECT DELAYS! UPCOMING TRAFFIC SWITCH: Northbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be shifted to the north for ongoing bridge work on Thursday, April 30 between 7:00 a.m. and 7:00 p.m. weather permitting. Both northbound and southbound U.S. 69 traffic will continue to travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge) during bridge construction work. Project work is scheduled to be completed on Thursday, April 30. (NEW 4-23-15) 

U.S. 73/K-7 Reconstruction Project Update

PROJECT RESTART! WEEKDAY LANE CLOSURES: KOSS Construction, project contractor, will resume work on the pavement reconstruction project on U.S. 73/K-7 from the north junction of Leavenworth County Road 14 south to 16th Street (Leavenworth County) beginning on Monday, April 27, weather permitting.  This upcoming Monday, April 27, crews will begin work including pavement patching on the Leavenworth County Road 14/Santa Fe Trail detour route and the addition of asphalt shoulders needed to construct the far north end part of the project.

> > Here’s what this means for drivers:  For the next two weeks, Monday, April 27-Friday, May 8, during daylight hours, there will be varying lane closures on the north end of U.S. 73/K-7 and on Leavenworth County Road 14/Santa Fe Trail. Traffic will be directed through the project work zone via flaggers during daytime working hours only, Monday-Friday.

Beginning on Monday, May 11, weather permitting, the Leavenworth County Road 14/Santa Fe Trail detour route will be reactivated and U.S. 73/K-7 traffic will begin utilizing the detour route that same day so that crews can complete final construction work on the U.S. 73/K-7 pavement reconstruction project. Advance separate notification will be sent to confirm the detour route reactivation date.

> > Remaining work to be completed on the project includes: replacement of the temporary rock shoulders with concrete pavement shoulders, and pavement replacement tie-in work at one intersection and an approximately 1/4-mile section of highway located at the north end of the project. Once this work is done, the detour route will be deactivated, U.S. 73/K-7 traffic will be shifted back to the existing roadway and overlay work will then begin on Leavenworth County Road 14/Santa Fe Trail. Project work is scheduled to be completed in mid-summer 2015. (NEW 4-24-15)

K-92 Centennial Bridge

EXPECT DELAYS! WEEKDAY LANE CLOSURES: Eastbound and westbound K-92 over the Centennial Bridge will be reduced to one lane for both directions for bridge inspection work on Monday-Wednesday, April 27-29 between 9:00 a.m. and 3:30 p.m. each day. Flaggers will direct traffic across the bridge. Project work is scheduled to be completed on Wednesday, April 29. (NEW 4-14-15) 

Missouri Route: I-29  > > KCI Airport Travel Impacts

EXPECT DELAYS! 24/7 LANE & RAMP CLOSURES: Motorists should prepare for delays as MoDOT crews work to rehabilitate 12 bridges along the I-29 corridor between I-435 and I-635 in Platte County, MO beginning on Tuesday, April 21 and continuing for six months. Work will cause lane reductions, narrow lanes, and ramp closures. Motorists should use alternate routes such as I-435 and U.S. 169. The following impacts will be underway: 

  • Two lanes of I-29 will be maintained in each direction between 112th Street and Route 45 (64th Street).
  • I-29 will be reduced to one lane at Route D (Cookingham Drive) for each direction for 80 calendar days.
  • The ramp from eastbound Route 152 to southbound I-29 will be closed for the duration of the project.
  • I-29 lanes will be narrowed at the bridge locations.

Temporary lane closures may be encountered on Route D (Cookingham Drive), 112th Street, Tiffany Springs Parkway, Barry Road, 72nd Street, and Route 45 (64th Street) during off peak hours. Project work is scheduled to be completed in Fall 2015. (REV. 4-20-15)

 

 

 

WYANDOTTE COUNTY

  

 

No short-term project closures at this time.

 

 


  

LONG TERM

  

Long term project closures listed below typically take place 24 hours a day, 7 days a week. Project completion dates typically range from 31 days up to a year. All closures and scheduled work are weather permitting and subject to change.

 

JOHNSON COUNTY 

 

 > > #Jocogateway 

Westbound I-435 from U.S. 69 to I-35

TRAFFIC SHIFT: Westbound I-435 traffic from U.S. 69 to just west of I-35 will be shifted to the south with three through and one auxiliary lane for reconstruction work on the westbound I-435 lanes, 24/7 round the clock, beginning on Thursday, September 4 through late 2014, weather permitting. Crews will begin setting traffic control at 8:00 p.m. on Wednesday, September 3 and the traffic shift will be in place before morning rush hour on Thursday, September 4, weather permitting. 

Westbound I-435 traffic (from U.S. 69 to just west of I-35) will travel through the work zone via three through lanes and one auxiliary lane as follows: 

1) Far left lane traffic will travel through the work zone only directed via concrete barrier on either side of the driving lane. Traffic will travel on an 11-foot wide driving lane with an approximate 2-foot left shoulder and 8-foot right shoulder (lane is located in former eastbound I-435 lane/median area).
2) Center lane traffic will travel through the work zone as normal
3) Right lane traffic will travel through the work zone as normal
4) Far right auxiliary lane will be used for traffic wishing to access the U.S. 69, Quivira Road and I-35 interchanges  

Advance message boards will alert drivers to the traffic shift. There will be an 11-foot lane width restriction and a 55 mph posted speed limit through the project work zone throughout the project duration. Note: Eastbound I-435 traffic through this area has already been shifted to the south slightly to accommodate the westbound I-435 traffic shift. All ramp access will remain open at the U.S. 69, Quivira Road and I-35 interchanges. Project work is scheduled to be completed in Spring 2015. (REV. 1-9-15)

K-10 & Renner Boulevard Interchange Project

EXPECT DELAYS! 24/7 ROAD & RAMP CLOSURES: All lanes of Renner Boulevard at K-10, eastbound K-10 to Renner Boulevard exit ramp and Renner Boulevard to eastbound K-10 entrance ramp will be CLOSED to all traffic, 24/7 round the clock, beginning sometime EARLY AFTERNOON on Tuesday, April 14, weather permitting. Renner Boulevard is scheduled to reopen in mid-September 2015, and the eastbound K-10  Renner Boulevard ramps are scheduled to reopening August 2015. SPECIAL NOTE: Renner Boulevard and the adjacent K-10 ramps will FULLY CLOSE once College Boulevard is opened to four-lanes of traffic which is planned for some time during the day nesxt Tuesday, April 14. Renner Boulevard at K-10 cannot fully close until College Boulevard is fully opened to four lanes of traffic. Marked detours will be provided. Project work is scheduled to be completed in Late Summer 2015. (REV. 4-13-15) 


I-35 from 151st Street to Santa Fe/135th Street Pavement Reconstruction Project
Overall project work is scheduled to be completed in December 2015

EXPECT DELAYS! 24/7 RAMP CLOSURES:  Northbound and southbound I-35 from just north of 151st Street to just north of Santa Fe Street/135th Street will have varying lane and ramp closures for reconstruction work beginning on Monday, March 16. Construction will be completed in two phases. Each phase will take approximately four months to complete, weather permitting. During the weeks of March 16-30, crews will begin project work by setting traffic control followed by construction of median crossovers located at either end of the project. Traffic impacts include lane reductions on I-35 and the closure of the Santa Fe Street/135th Street to southbound I-35 entrance ramp throughout the project duration. Ramp closures and lane reductions are tentatively scheduled to begin sometime around Monday, March 30, weather permitting. Phase One. All I-35 traffic will be carried on the existing northbound lanes separated by concrete barrier while the southbound lanes are reconstructed. During this phase, the southbound I-35 to Old U.S. 56 exit ramp will be closed. Southbound I-35 to Old U.S. 56 ramp traffic will detour via the U.S. 169/K-7 exit then north on K-7 to Old U.S. 56. Approximate timeframe for completion work on this phase: April-July 2015, weather permitting. Phase Two. All I-35 traffic will be carried on the newly completed southbound lanes separated by concrete barrier while the northbound lanes are reconstructed. During this phase, the Old U.S. 56 to northbound I-35 entrance ramp and the northbound I-35 to Santa Fe Street/135th Street exit ramp will be closed. Approximate timeframe for completion work on this phase: August-December 2015, weather permitting. Santa Fe Street/135th Street to southbound I-35 ramp traffic will detour via Mur-Len Road south to 151st Street west to I-35 or via Ridgeview Road north to 119th Street east to I-35. Project work is scheduled to be completed in late December 2015. (NEW 3-18-15)

U.S. 69 & 159th Street Interchange Project

EXPECT MAJOR DELAYS! 24/7 LANE CLOSURE: Northbound U.S. 69 from 167th Street to 159th Street will be reduced to ONE OPEN LANE for ramp lane construction work, 24/7 round the clock, beginning on Thursday, April 16 through late September 2015. Project work is scheduled to be completed in late September 2015. (NEW 4-6-15) 

24/7 LANE CLOSURE: Eastbound 159th left lane from Lowell Avenue to U.S. 69 will be CLOSED for bridge work beginning on Wednesday, March 4, 24/7 round the clock.  Project work is scheduled to be completed in Spring 2015. (NEW 3-4-15)

24/7 LANE CLOSURE: Westbound 159th left lane from Foster Street to U.S. 69 will be CLOSED for bridge work beginning on Friday, February 13, 24/7 round the clock.  Project work is scheduled to be completed in Spring 2015. (NEW 2-16-15)

WEEKDAY LANE/SHOULDER CLOSURES: Northbound and southbound U.S. 69 from 151st Street to 169th Street may have periodic lane and shoulder closures for ramp construction work beginning in September 2014 through late October 2015. KDOT partnered on a city-led project with the City of Overland Park for the U.S. 69 & 159th Street interchange expansion project. This expansion project includes the addition of interchange ramps to the existing intersection at U.S. 69 and 159th Street in Overland Park (Johnson County). The project work zone on northbound and southbound U.S. 69 will extend from 151st Street south to 169th Street throughout the duration of the project. Construction work, including periodic lane and shoulder closures, will primarily occur during daylight hours Monday through Friday. Project work is scheduled to be completed in late October 2015. (NEW 12-15-14)

 

 

LEAVENWORTH COUNTY

 

 No long-term project closures at this time.

 

 

WYANDOTTE COUNTY

 

I-70 Multi-Bridge Repair Project
Overall project work is scheduled to be completed in December 2015

EXPECT DELAYS! 24/7 LANE & RAMP CLOSURES: The following ramp closures will begin: northbound and southbound I-635 to eastbound I-70 and eastbound I-70 to Park Drive/Kaw Drive, 24/7 round the clock, beginning at 7:00 p.m. on Thursday, March 26 for bridge deck replacement and repair work. Marked detours will be provided. At 3:00 p.m. on Saturday, March 28, eastbound and westbound I-70 from just west of I-635 to just east of Kaw Drive will be reduced to two 11-foot lanes with no shoulders, 24/7 round the clock, throughout the project duration.The northbound and southbound I-635 to eastbound I-70 ramp closures will be in place, 24/7 round the clock, throughout the project duration. Project construction information, including general phasing, traffic impacts and marked detour route maps can be viewed at: I-70 over Kaw Drive Multi-Bridge Construction Project Handout. The eastbound I-70 to Park Drive/Kaw Drive ramp will reopen to traffic in July 2015. The overall project work is scheduled to be completed in late December 2015. (REV. 3-27-15)

U.S. 69 over Missouri River Bridge Replacement Project (MoDOT/KDOT Project) > #us69moriverbridge
Overall project work is scheduled to be completed in December 2016

24/7 LANE CLOSURES: Northbound and southbound U.S. 69 from I-635 (in Missouri) to Kindleberger Road in Kansas will be reduced to one lane in each direction, 24/7, beginning on Friday, October 24 for bridge replacement work. Both northbound and southbound U.S. 69 traffic will travel on the existing northbound U.S. 69 bridge (Platte Purchase Bridge). A crossover will be used to shift southbound U.S. 69 traffic to the existing Platte Purchase Bridge. The traffic switch is scheduled for Friday, October 31, 2014 and traffic will remain in this configuration until Thursday, December 1, 2016. Project work is scheduled to be completed on Thursday, December 1, 2016. (NEW 10-27-14)